Edged Energy: Chicago ORD03

2725 Bilter Rd

Operated by:

The new data center campus, known as Aurora TechPark, facility will offer 100 MW of capacity built to handle dense AI-driven workloads on their way to transforming the IT industry.

  • Located on 65 acres at the southwest corner of Bilter Road and Eola Road in Aurora, the new multi-building data center campus is being designed with waterless cooling and energy-efficient systems for enabling a PUE rating of 1.15.
  • The campus will be constructed in three phases, with the first building ORD01 scheduled for completion in June 2024 with 24MW capacity.
  • The second building ORD02 will be the largest one with 48 MW capacity.
  • The third building ORD03 will have 24MW capacity.
  • The site reflects a collaboration between Edged Energy, real estate developer Seefried Industrial Properties and local utility provider ComEd.

Map and Nearby Locations:

2725 Bilter Rd
Click Map to begin Search

Sites within 15 miles of Edged Energy: Chicago ORD03

Show SqM
Distance Site About
0.12 miles Edged Energy: Chicago ORD02
The new data center campus, known as Aurora TechPark, facility will offer 100 MW of capacity built to handle dense AI-driven workloads on their way to transforming the IT industry.
0.30 miles Edged Energy: Aurora, Chicago
The new data center campus, known as Aurora TechPark, facility will offer 100 MW of capacity built to handle dense AI-driven workloads on their way to transforming the IT industry.
0.51 miles CyrusOne Chicago Aurora CME
In 2016, CyrusOne acquired the CME data center for $130 million. CME hosts its electronic trading platform CME Globex on site. Globex will continue to be hosted on site as part of the 15-year lease agreement between CyrusOne and CME.
2.55 miles NetSource Chicago
2.59 miles 4267 Meridian Pkwy: Lincoln Rackhouse
The facility was acquired when Lincoln Rackhouse acquired Bytegrid in 2019.
4.99 miles New Continuum: 603 Discovery
5.14 miles Cogent Naperville
7.67 miles Evoque Lisle CH1
11.47 miles CyrusOne Chicago Lombard
9 MW of critical capacity Both a 1.5MW and a 2MW transformer
12.54 miles 360TCS-Lombard
12.54 miles Digital Fortress: Chicago Lombard
13.97 miles Equinix Chicago CH7
15.80 miles NYI Chicago (Oak Brook)
15.93 miles US Signal Oakbrook
800a 480V 3 phase 450kW diesel generator with 24 hour run time at full load 500kVa UPS capacity with battery backup
15.93 miles Verizon: (Oak Brook)
15.93 miles Server Farm Oak Brook
The campus was originally built as the corporate headquarters of the Chicago Bridge & Iron Company (CB&I).
16.97 miles LexusNexis Oak Brook
16.98 miles Verizon: Swift Dr
16.98 miles DataBank (ORD4) Oak Brook
17.45 miles NTT Chicago CH1
RagingWire’s Chicago CH1 Data Center is under construction and in the pre-leasing stage. It will be a 654,000 square foot, 52 megawatt facility on a 19-acre fenced campus near Chicago.
17.75 miles NTT: 1200 N Arlington Heights (Planned)
Expansion site acquired in November 2023.
17.78 miles NTT: 1250 N Arlington Heights (Planned)
In November 2023, NTT Global Data Centers in November paid $27.5 million for the building
18.38 miles Aligned ORD-02
Aligned's ORD-02 is a data center located in Northlake, IL near downtown Chicago. Part of Aligned's 18.5-acre hyperscale campus, ORD-02 offers exceptional connectivity at the convergence of over 12 metro/long-haul networks. At full build, ORD-02 building will provide 36MW of critical load capacity expandable to ~52 MW.
18.43 miles Aligned Chicago ORD-01
Aligned's ORD-01 data center is a state-of-the-art facility located in Northlake, IL, just outside of downtown Chicago. At full build, Aligned’s Chicago campus covers 520,000 sq. ft. and offers ~72 MW of critical load.
18.45 miles Element Critical CH2
Element Critical acquired the site in January 2019 from Sungard. The facility was previously known as SunGard Wood Dale (341).
18.56 miles Microsoft Chicago Northlake
18.62 miles Element Critical CH1
Element Critical acquired the site in January 2019 from Sungard. The facility was previously known as SunGard Wood Dale (711).
18.69 miles Compass Hoffman Estates
18.84 miles 505 N Railroad Ave - Digital Realty
The Digital Chicago Campus covers 21 acres of land with access to major fiber networks and can support up to 8 MW of IT load at N+1 redundancies.
19.04 miles Skybox Chicago I
19.09 miles T5 Northlake IL
19.47 miles 1450 E Devon Ave (CH3) DRT
19.49 miles Microsoft Hoffman Estates 2
19.57 miles Digital Elk Grove Village Campus
Digital Realty Trust's Chicago campus is massive and is split among 3 buildings. The campus was acquired from Dupont Fabros in September 2017.
19.57 miles ServerCentral CH1
19.57 miles HostPapa CH1
Formerly known as "ColoCrossing CH1"
19.57 miles Rackspace Elk Grove ORD1
19.57 miles 2200 Busse Rd (CH1) DRT
19.60 miles Complete Source Schaumburg
19.65 miles Cyxtera Elk Grove CH3
Cyxtera's CH3 Elk Grove site is across the street from the Digital Realty Chicago campus (former Dupont Fabros) and close to Equinix CH3.
19.71 miles 2299 Busse (CH2) Digital Realty
19.72 miles CoreWeave: US Central ORD1
19.80 miles Microsoft Hoffman Estates 1
19.94 miles Stream Chicago II
Stream Data Centers' Chicago II data center in Elk Grove Village, Illinois is a 226,000 square foot facility.

Edged Energy: Chicago ORD03 Data Center Photos

Operating Company

Edged Energy is a colocation and data center provider. The company also has data centers in development across the US.

Its Spain business is a subsidiary of Endeavour in collaboration with Merlin Properties.

13 Facilities Owned